CERC Capital cost norms for solar PV for FY 13-14


CERC has provided the following breakup of benchmark capital cost norm for solar PV projects for FY13-14.

S.No. Particulars Capital cost norm for solar PV project (Rs.lakhs/MW) % of total cost
1 PV Modules 344.50 43%
2 Land cost 16.80 2%
3 Civil and General works 94.50 12%
4 Mounting structures 105.00 13%
5 Power Conditioning Unit (PCU) 60.00 7%
6 Evacuation cost upto Interconnection point (Cables and Transformers) 105.00 13%
7 Preliminary and pre-operative expense including IDC and contingency 80.00 10%
8 Total Capital Cost 805.80 100%

Asim Sharma, Consultant, Firstgreen Consulting

Advertisements

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s